Post Featured Image

Week 5 Progress

As we turn the calendar to October our project is progressing well, with highly visible changes from week to week.  In the past week crews were able to pour the concrete floor, remove the soffit from the existing building, and begin laying the block restroom walls.  For pictures of the volunteers and construction crews in action, click here.

In the coming week we expect to finish laying the block walls for the restrooms and reinforce them to serve as a storm shelter for the building.  Metal decking will be laid across the walls and then concrete poured to form a cap over the storm shelter, which will be the floor of the kid's loft.  If we continue to be blessed with good progress and fair weather we could see wall and roof framing start as soon as late next week.

Thanks for your continued prayerful support.